Action Ministry’s new administration office has come along way since this project began roughly two months ago.  The building has been constructed and is nearing completion.  Action Ministry’s staff can now use the upstair’s room to hold their staff meetings in. Having a permanent administration office at Blessed Camp is going to be a huge help to Action Ministry.  This will provide them with a central location to better care for the residents of Blessed Camp.

Still remaining to be completed are the ceilings and painting.  The budget for this project was $11,000.  So far we have been able to raise $10,000 towards it.  If you would like to help us raise the final $1,000 and finish this project you can donate by clicking the red “View Need” button at the top.

Thank you!